MacKay was the successful contractor to complete the Mount Michael access road construction and pre-bench construction.
The contract stipulated that the proponent complete 2,500,000 cubic meters of earthwork in 168 calendar days. MacKay completed this work in 70 days, exceeding the schedule by just over three months.